Oracle sends force majeure notice on its New Mexico Stargate
The notice would allow Oracle to delay payments should the facility miss its 2028 target to come online.
Key Takeaways
- →Oracle has sent a force majeure notice to the developer of Project Jupiter, a Stargate data center campus in New Mexico, Bloomberg first reported Thur
- →Force majeure clauses, common in energy and commodities contracts, excuse a party from contractual obligations when events outside its control get in
- →Oracle is not seeking to exit as the campus’s main tenant, according to Bloomberg’s sources
- →Instead, the notice would allow the company to delay payments should the facility miss its 2028 target to come online
- →The notice also comes as AI data center construction faces growing scrutiny nationally, and as developers take on steep costs to build capacity for cu
Key Takeaways
- Oracle has sent a force majeure notice to the developer of Project Jupiter, a Stargate data center campus in New Mexico, Bloomberg first reported Thur
- Force majeure clauses, common in energy and commodities contracts, excuse a party from contractual obligations when events outside its control get in
- Oracle is not seeking to exit as the campus’s main tenant, according to Bloomberg’s sources
- Instead, the notice would allow the company to delay payments should the facility miss its 2028 target to come online
- The notice also comes as AI data center construction faces growing scrutiny nationally, and as developers take on steep costs to build capacity for cu
Oracle has sent a force majeure notice to the developer of Project Jupiter, a Stargate data center campus in New Mexico, Bloomberg first reported Thursday.
Force majeure clauses, common in energy and commodities contracts, excuse a party from contractual obligations when events outside its control get in the way. Oracle is not seeking to exit as the campus’s main tenant, according to Bloomberg’s sources. Instead, the notice would allow the company to delay payments should the facility miss its 2028 target to come online.
The notice also comes as AI data center construction faces growing scrutiny nationally, and as developers take on steep costs to build capacity for customers like OpenAI.
Oracle maintains that it does not expect a delay. “Project Jupiter remains on our planned schedule,” Oracle said in a statement to CNBC. “We are fully committed to New Mexico and confident in our path forward.”
Blue Owl Capital, whose unit received the notice, said in its own statement to CNBC that “this notice does not change the financial commitments to this multi-year project.”
Neither Oracle nor Blue Owl immediately responded to TechCrunch’s requests for comment.
Still, the notice follows a string of setbacks at the site, many of them tied to its energy supply. The campus, designed to handle 2.45 gigawatts, is meant to run on gas-powered fuel cells from Bloom Energy, which makes a reliable gas supply central to its timeline.
An Energy Transfer pipeline intended to deliver gas to the site has also been delayed nearly six months, to February 1, 2027, after regulators repeatedly denied permits for the line. In August, Bloomberg reported that the pipeline’s route had been changed following those rejections. A separate air-quality permit for the fuel cell system that would power the campus is also pending. The state’s environment department faces a November 23 deadline to decide.
Project Jupiter is one of the flagship sites of Stargate, the AI infrastructure initiative Oracle, OpenAI, and SoftBank announced with President Donald Trump early in his second term. The campus has drawn opposition from residents and environmental groups and has become a political flashpoint ahead of the midterm elections. Oracle has responded with a public outreach campaign in the state aimed at winning over the project’s critics, according to Bloomberg.
When you purchase through links in our articles, we may earn a small commission. This doesn’t affect our editorial independence.
Aditya Mehta is a reporter at TechCrunch covering AI. He’s supported by the Tarbell Center for AI Journalism and attended UC Berkeley. You can contact from Aditya by emailing aditya.mehta@techcrunch.com or via encrypted message at adymehta.74 on Signal.
Frequently Asked Questions
What is Oracle sends force majeure notice on its?
The notice would allow Oracle to delay payments should the facility miss its 2028 target to come online.
Originally reported by TechCrunch. Enhanced and optimized for search by TechVeb.
Frequently Asked Questions
What is Oracle sends force majeure notice on its?
Stay in the loop
Get the latest tech news and AI insights delivered to your inbox. No spam, unsubscribe anytime.
TechVeb Team
Your trusted source for the latest in technology, AI innovations, and digital trends. We bring you in-depth analysis, expert reviews, and comprehensive guides.
Learn more about us →More cybersecurity News
Pakistan in uncharted waters as ‘super El Nino’ multiplies t
• 2027 most likely to become hottest year ever• El Nino may impact monsoon, bring droughts to southern provinces; can cause 451,000 extra deaths ISLAMABAD: With
Hacking group ShinyHunters claims it breached the FBI, stole
The theft of agents' personal information could present a major counterintelligence threat, where agents and their families are extorted into cooperating with a
Iran must stop arming Houthis in Yemen, G7 says ahead of UN
The G7 also condemns "in the strongest terms" Houthi attacks on Saudi Arabia, saying that the escalation in fighting in Yemen jeopardises global energy securi